Moving an existing sprint to another project is not currently available. Copy it into the target project instead.
In earlier versions you could change a sprint's project from the sprint form. This option is not currently available: the edit sprint form has no project field, and the sprint menus have no action to change the project. A sprint is linked to a project only when you create it from that project's page.
Before you start
- Move to folder in the sprint row menu only moves a sprint between folders. It does not change its project.
- Move to Team moves a personal sprint into a team workspace. It does not change its project either.
Steps
Use this workaround to get the same sprint into another project:
- Open the target project and click Create sprint.
- Under Make a sprint from, select Previous.
- Pick the sprint you want to move from the dropdown.
- Enter a Name (required). You can reuse the original name.
- Click Create a Sprint. The new sprint is linked to the project and contains a copy of every session, with agenda items and resources.
- Go back to the original sprint and click Archive, or use Delete in the ... menu next to its name if you no longer need it.
Tips
- Check the copy before you delete the original. Deleting a sprint also deletes its sessions.
- Archiving is safer than deleting: you can always unarchive the original later.
If you need help with this, contact SolveNext support.